When is a Plan for Improvement (PFI) change request necessary?
A change request is necessary with any of the following:
1. Request for an extension to a previously approved projected completion date.
2. Request to modify values in a previously approved PFI
3. Traditional equivalency and fire safety evaluation system (FSES) requests
All equivalencies must be submitted in writing, with appropriate supporting documentation. Follow the “PFI change request” procedure that is accessed in the navigation menu under “PFI” located in your organization’s Statement of Conditions TM (SOC).